Phase / Level 2 - Pre-Functional & Component Verification

- Installation verification against IFC drawings (single-line, layouts)
- Component testing (UPS, switchgear, cooling, sensors, protection)
- Verification of measurement points, alarms and interfaces
- Basis for subsequent functional testing

Phase / Level 3 - Functional Performance Testing

- Verification of system functions and control sequences
- Testing of normal and abnormal operation (load, bypass, failover)
- Confirmation of redundancy and protection functions
- Documentation of functional performance against design intent

Phase / Level 4 - Integrated Systems Testing (IST)

- Verification of interaction between power, cooling and control systems
- Simulation of fault scenarios and utility failures
- Verification of transfer, recovery and stable operation
- Final validation prior to Interim and Final Acceptance